NewPix





Project Start:
Project Finish:
Thu 6/18/98
Wed 1/16/02


Tasks


IDWBSTask NameDurationStartFinish
21.1.1R&D Baseline Lehman Review0 dThu 10/8/98Thu 10/8/98
31.1.1Internal Progress Review #10 dFri 3/5/99Fri 3/5/99
41.1.1Internal Progress Review #20 dWed 12/15/99Wed 12/15/99
51.1.1Production Baseline Review/Funding Release0 dMon 5/29/00Mon 5/29/00
181.1.1.1.1Sector PDR0 dWed 9/1/99Wed 9/1/99
191.1.1.1.1ID Engr Review at CERN0 dTue 10/20/98Tue 10/20/98
211.1.1.1.1Select Sector Baseline Concept0 dWed 9/1/99Wed 9/1/99
221.1.1.1.1PRR for Sectors0 dWed 5/3/00Wed 5/3/00
261.1.1.1.1Disk PDR0 dWed 5/3/00Wed 5/3/00
281.1.1.1.1Disk PRR0 dFri 2/2/01Fri 2/2/01
301.1.1.1.1Module Attach CDR0 dWed 9/1/99Wed 9/1/99
321.1.1.1.1Module Attach PDR0 dWed 5/3/00Wed 5/3/00
341.1.1.1.1Module Attach PRR0 dFri 2/2/01Fri 2/2/01
361.1.1.1.1Support Struct CDR0 dWed 5/3/00Wed 5/3/00
381.1.1.1.1Support Structure PDR0 dFri 2/2/01Fri 2/2/01
401.1.1.1.1Support Structure PRR0 dWed 1/16/02Wed 1/16/02
521.1.1.1.2Compl Testing of 5-Disk Protos0 dWed 9/1/99Wed 9/1/99
551.1.1.1.2Compl Testing of Disk Prototypes0 dTue 12/21/99Tue 12/21/99
581.1.1.1.2Compl Test of Proto Module Attach0 dWed 5/3/00Wed 5/3/00
611.1.1.1.2Compl Test of Support Structure Protos0 dFri 2/2/01Fri 2/2/01
731.1.1.2.1Second prototype PDR0 dTue 12/1/98Tue 12/1/98
741.1.1.2.1Second prototype FDR0 dMon 3/29/99Mon 3/29/99
751.1.1.2.1Compl Second Prototype Design0 dTue 4/27/99Tue 4/27/99
771.1.1.2.1Sensor Final Design Review0 dThu 1/20/00Thu 1/20/00
781.1.1.2.1Compl Preproduction Design0 dWed 7/19/00Wed 7/19/00
901.1.1.2.2Compl Testing First Protos0 dTue 4/13/99Tue 4/13/99
921.1.1.2.2Compl Fabr of Second Protos0 dTue 9/21/99Tue 9/21/99
941.1.1.2.2Compl Testing Second Protos0 dThu 1/20/00Thu 1/20/00
971.1.1.2.3Start Market Survey0 dMon 11/2/98Mon 11/2/98
981.1.1.2.3Complete Market Survey0 dFri 3/5/99Fri 3/5/99
991.1.1.2.3Select Production Detector Type0 dThu 1/20/00Thu 1/20/00
1001.1.1.2.3Select Detector Vendor(s)0 dThu 1/20/00Thu 1/20/00
1011.1.1.2.3Start Preproduction Procurement0 dThu 2/24/00Thu 2/24/00
1021.1.1.2.3Complete Preproduction Procurement0 dThu 6/22/00Thu 6/22/00
1041.1.1.2.3Complete Preproduction Fabrication0 dWed 12/13/00Wed 12/13/00
1061.1.1.2.3Compl Preprod Testing0 dTue 5/29/01Tue 5/29/01
1181.1.1.3.1Final Design Review DMILL Rad-Hard Proto0 dMon 1/25/99Mon 1/25/99
1191.1.1.3.1Compl Design DMILL Rad-Hard Proto0 dFri 2/26/99Fri 2/26/99
1211.1.1.3.1Compl Des Honeywell Rad-Hard Test Devices0 dThu 4/16/98Thu 4/16/98
1231.1.1.3.1Final Design Review Honeywell 1st Proto0 dFri 3/5/99Fri 3/5/99
1241.1.1.3.1Compl Des Honeywell FE Rad-Hard Proto0 dFri 4/2/99Fri 4/2/99
1261.1.1.3.1Final Design Review of 2nd Rad-Hard Proto0 dMon 6/12/00Mon 6/12/00
1271.1.1.3.1Compl Des 2nd Rad-Hard Proto0 dFri 7/7/00Fri 7/7/00
1391.1.1.3.2Compl Fabr of Honeywell Sol Test Devices0 dWed 8/26/98Wed 8/26/98
1421.1.1.3.2Compl Fabr of DMILL Proto0 dFri 7/23/99Fri 7/23/99
1441.1.1.3.2Compl Testing DMILL Prototype0 dThu 12/9/99Thu 12/9/99
1461.1.1.3.2Compl Fabr Honeywell Protos0 dWed 8/25/99Wed 8/25/99
1481.1.1.3.2Compl Testing Honeywell Prototype0 dTue 2/15/00Tue 2/15/00
1491.1.1.3.2Review Design Approach0 dWed 1/19/00Wed 1/19/00
1501.1.1.3.2Vendor Selection0 dTue 2/29/00Tue 2/29/00
1521.1.1.3.2Compl Fabr of 2nd Rad-Hard Proto0 dWed 11/29/00Wed 11/29/00
1541.1.1.3.2Compl test 2nd Rad-Hard Proto0 dThu 3/29/01Thu 3/29/01
1651.1.1.4.1Compl First Proto Design0 dTue 9/1/98Tue 9/1/98
1661.1.1.4.11st Prototype Design Review0 dThu 2/18/99Thu 2/18/99
1681.1.1.4.12nd Prototype Design Review0 dWed 4/28/99Wed 4/28/99
1691.1.1.4.1Compl Second Proto Design0 dTue 5/25/99Tue 5/25/99
1711.1.1.4.13rd Prototype Design Review0 dMon 7/10/00Mon 7/10/00
1721.1.1.4.1Compl Third Prototype Design0 dFri 8/4/00Fri 8/4/00
1821.1.1.4.2Compl Fabr/Assy of 1st Proto0 dThu 1/14/99Thu 1/14/99
1841.1.1.4.2Compl Tests of First Protos0 dThu 4/15/99Thu 4/15/99
1851.1.1.4.2Select Hybrid Type0 dThu 4/15/99Thu 4/15/99
1881.1.1.4.2Compl Tests of 2nd Prototypes0 dTue 2/8/00Tue 2/8/00
1891.1.1.4.2Select Hybrid Prod Vendor(s)0 dTue 2/8/00Tue 2/8/00
1921.1.1.4.2Compl Tests of 3rd Proto Hybrids0 dTue 10/24/00Tue 10/24/00
2031.1.1.5.1Compl First Prototype Design0 dThu 10/29/98Thu 10/29/98
2041.1.1.5.11st Prototype Design Review0 dThu 2/18/99Thu 2/18/99
2061.1.1.5.12nd Prototype Design Review0 dFri 9/17/99Fri 9/17/99
2071.1.1.5.1Compl 2nd Proto Design0 dThu 10/14/99Thu 10/14/99
2091.1.1.5.13rd Prototype Design Review0 dMon 10/2/00Mon 10/2/00
2101.1.1.5.1Compl 3rd Proto Design0 dFri 10/27/00Fri 10/27/00
2211.1.1.5.2Compl Tests of First Protos0 dThu 3/18/99Thu 3/18/99
2221.1.1.5.2Select Module Type0 dThu 3/18/99Thu 3/18/99
2251.1.1.5.2Compl Tests of 2nd Prototypes0 dMon 4/3/00Mon 4/3/00
2261.1.1.5.2Select Module Prod Vendor(s)0 dMon 4/3/00Mon 4/3/00
2291.1.1.5.2Compl Tests of 3rd Proto Modules0 dFri 9/28/01Fri 9/28/01



Assignments


Task IDTask NameResource NameWorkStartFinish% Work Complete
10FY96 Prior Scheduled Activities ResourcesLBLj ME PRJ368 hrsMon 9/2/96Mon 9/30/960%
14Design FY00 Mat'l/Labor $'sLBLj ME PRJ1,431 hrsFri 10/1/99Fri 9/29/000%
13Design FY99 Mat'l/Labor $'sLBLj ME PRJ1,726 hrsThu 10/1/98Thu 9/30/990%
12Design FY98 Mat'l/Labor $'sLBLj ME PRJ1,207 hrsWed 10/1/97Wed 9/30/980%
12Design FY98 Mat'l/Labor $'sLBLj PM PRJ0 hrsWed 10/1/97Wed 10/1/970%
11Design FY97 Mat'l/Labor $'sLBLj ME PRJ906 hrsTue 10/1/96Tue 9/30/970%
46Developments FY98 Mat'l/Labor $'sLBLs MT PRJ332 hrsWed 10/1/97Wed 9/30/980%
46Developments FY98 Mat'l/Labor $'sLBLs PM PRJ0 hrsWed 10/1/97Wed 10/1/970%
48Developments FY00 Mat'l/Labor $'sLBLs MT PRJ560 hrsFri 10/1/99Fri 9/29/000%
48Developments FY00 Mat'l/Labor $'sLBLs PM PRJ0 hrsFri 10/1/99Fri 10/1/990%
47Developments FY99 Mat'l/Labor $'sLBLs MT PRJ672 hrsThu 10/1/98Thu 9/30/990%
47Developments FY99 Mat'l/Labor $'sLBLs PM PRJ0 hrsThu 10/1/98Thu 10/1/980%
45FY97 Prior Scheduled Activities ResourcesLBLs PM PRJ0 hrsTue 10/1/96Tue 10/1/960%
44FY96 Prior Scheduled Activities ResourcesLBLs PM PRJ0 hrsSun 9/1/96Sun 9/1/960%
67Design FY97 Mat'l/Labor $'sUNM SP PRJ880 hrsTue 10/1/96Tue 9/30/970%
69Design FY99 Mat'l/Labor $'sUNM SP PRJ240 hrsThu 10/1/98Thu 9/30/990%
70Design FY00 Mat'l/Labor $'sUNM SP PRJ240 hrsFri 10/1/99Wed 7/19/000%
82Development FY97 Mat'l/Labor $'sSUNYA PM MC 0 hrsMon 9/1/97Mon 9/1/970%
82Development FY97 Mat'l/Labor $'sUNM PM PRJ0 hrsMon 9/1/97Mon 9/1/970%
85Development FY00 Mat'l/Labor $'sUNM ST PRJ1,000 hrsFri 10/1/99Thu 1/20/000%
85Development FY00 Mat'l/Labor $'sUNM PM PRJ0 hrsFri 10/1/99Fri 10/1/990%
84Development FY99 Mat'l/Labor $'sUNM ST PRJ1,000 hrsThu 10/1/98Thu 9/30/990%
84Development FY99 Mat'l/Labor $'sUNM PM PRJ0 hrsThu 10/1/98Thu 10/1/980%
83Development FY98 Mat'l/Labor $'sSUNYA PM MC 0 hrsWed 10/1/97Wed 10/1/970%
83Development FY98 Mat'l/Labor $'sUNM PM PRJ0 hrsWed 10/1/97Wed 10/1/970%
112Design FY97 Mat'l/Labor $'sLBLj EE PRJ675 hrsMon 3/3/97Tue 9/30/970%
115Design FY00 Mat'l/Labor $'sLBLj EE PRJ1,200 hrsFri 10/1/99Fri 7/7/000%
114Design FY99 Mat'l/Labor $'sLBLj EE PRJ1,200 hrsThu 10/1/98Thu 9/30/990%
113Design FY98 Mat'l/Labor $'sLBLj EE PRJ430 hrsWed 10/1/97Wed 9/30/980%
131FY96 Prior Scheduled Activities ResourcesLBLs PM PRJ0 hrsSun 9/1/96Sun 9/1/960%
133Development FY98 Mat'l/Labor $'sLBLs PM PRJ0 hrsWed 10/1/97Wed 10/1/970%
135Development FY00 Mat'l/Labor $'sLBLs PM PRJ0 hrsFri 10/1/99Fri 10/1/990%
134Development FY99 Mat'l/Labor $'sLBLs PM PRJ0 hrsThu 10/1/98Thu 10/1/980%
161Design FY98 Mat'l/Labor $'sUOK EE PRJ176 hrsWed 10/1/97Wed 9/30/980%
163Design FY00 Mat'l/Labor $'sUOK EE PRJ176 hrsFri 10/1/99Fri 8/4/000%
163Design FY00 Mat'l/Labor $'sUOK TR PRJ0 hrsFri 10/1/99Fri 10/1/990%
162Design FY99 Mat'l/Labor $'sUOK EE PRJ176 hrsThu 10/1/98Thu 9/30/990%
162Design FY99 Mat'l/Labor $'sUOK TR PRJ0 hrsThu 10/1/98Thu 10/1/980%
160FY97 Prior Scheduled Activities ResourcesUOK EE PRJ616 hrsMon 9/1/97Tue 9/30/970%
176FY97 Prior Scheduled Activities ResourcesUOK PM PRJ0 hrsMon 9/1/97Mon 9/1/970%
177Development FY98 Mat'l/Labor $'sUOK ST PRJ120 hrsWed 10/1/97Wed 9/30/980%
177Development FY98 Mat'l/Labor $'sUOK PM PRJ0 hrsWed 10/1/97Wed 10/1/970%
179Development FY00 Mat'l/Labor $'sSUNYA ST MC 500 hrsFri 10/1/99Fri 9/29/000%
179Development FY00 Mat'l/Labor $'sSUNYA PM MC 0 hrsFri 10/1/99Fri 10/1/990%
179Development FY00 Mat'l/Labor $'sUOK ST PRJ500 hrsFri 10/1/99Fri 9/29/000%
179Development FY00 Mat'l/Labor $'sUOK PM PRJ0 hrsFri 10/1/99Fri 10/1/990%
178Development FY99 Mat'l/Labor $'sSUNYA ST MC 500 hrsThu 10/1/98Thu 9/30/990%
178Development FY99 Mat'l/Labor $'sSUNYA PM MC 0 hrsThu 10/1/98Thu 10/1/980%
178Development FY99 Mat'l/Labor $'sUOK ST PRJ500 hrsThu 10/1/98Thu 9/30/990%
178Development FY99 Mat'l/Labor $'sUOK PM PRJ0 hrsThu 10/1/98Thu 10/1/980%
200Design FY00 Mat'l/Labor $'sLBLj EE PRJ400 hrsFri 10/1/99Fri 9/29/000%
200Design FY00 Mat'l/Labor $'sLBLs TR PRJ0 hrsFri 10/1/99Fri 10/1/990%
199Design FY99 Mat'l/Labor $'sLBLj EE PRJ100 hrsThu 10/1/98Thu 9/30/990%
199Design FY99 Mat'l/Labor $'sLBLs EE PRJ100 hrsThu 10/1/98Thu 9/30/990%
199Design FY99 Mat'l/Labor $'sLBLs TR PRJ0 hrsThu 10/1/98Thu 10/1/980%
214FY97 Prior Scheduled Activities resourcesLBLs PM PRJ0 hrsMon 9/1/97Mon 9/1/970%
215Development FY98 Mat'l/Labor $'sLBLs PM PRJ0 hrsWed 10/1/97Wed 10/1/970%
217Development FY00 Mat'l/Labor $'sLBLs ST PRJ150 hrsFri 10/1/99Fri 9/29/000%
217Development FY00 Mat'l/Labor $'sLBLs PM PRJ0 hrsFri 10/1/99Fri 10/1/990%
216Development FY99 Mat'l/Labor $'sLBLs ST PRJ150 hrsThu 10/1/98Thu 9/30/990%
216Development FY99 Mat'l/Labor $'sLBLs PM PRJ0 hrsThu 10/1/98Thu 10/1/980%